Text on the drawing
EIFS: 2" EPS OVER DRAINAGE MAT & FLUID-APPLIED WRB, MESH & FINISH COAT STARTER TRACK W/ WEEPS & FLASHING, 6" ABOVE GRADE 1/2" GLASS-MAT SHEATHING FINISH GRADE 600S162-43 STUDS @ 16" O.C. 5/8" TYPE X GYPSUM BOARD, #6 SCREWS @ 12" O.C. 600T125-43 BOTTOM TRACK ON SILL SEALER, #8 EA. FLANGE TO STUD EXTERIOR BEARING WALL, ONE STORY + ROOF. FOOTING SIZE AND REINFORCING PER FOUNDATION DETAILS. ISOLATE TRACK FROM CONCRETE W/ SILL SEALER; G60 MIN. COATING, G90 WITHIN 12" OF GRADE IN WET LOCATIONS. 1/2" DIA. A.B. @ 4'-0" O.C. W/ 3"X3"X1/4" PLATE WASHER, 7" EMBED N.T.S.